ClvFloor TC 104
Two-Component, Water-Based, Polyurethane-Based, Matt, Transparent Top Coat
ClvFloor TC 104 is a water-based, two-component, low-VOC, matt, transparent polyurethane top coat for floors
• UV-resistant, non-yellowing. • Water-based, low VOC. • Easy to clean. • Very low odour

FEATURES AND BENEFITS
-
• UV-resistant, non-yellowing.
• Water-based, low VOC.
• Easy to clean.
• Very low odour.
APPLICATION NOTES
-
The freshly applied coating must be protected from damp, condensation and water for at least 7 days (+20 °C). Before application, make sure the surface is even and clean; thin top coats do not conceal surface irregularities. On epoxy-based surfaces, sanding is recommended for good adhesion; a green pad can be used for this purpose. If heating is required, only electric warm-air blower systems should be used. Gas, oil, paraffin or other fossil-fuel heaters produce CO2 and H2O vapour, which adversely affects the surface appearance.
Product Details
0.15–0.20 kg/m²
Comp. A (metal pail): 6.00 kg Comp. B (metal pail): 1.50 kg Kit (A+B): 7.50 kg
Store the product in its unopened original packaging at temperatures between +5 °C and +25 °C for a maximum of 12 months. Once opened, use the product as soon as possible.
| Property | Test Method | Value |
|---|---|---|
| Chemical Base | Clever Lab. | Polyurethane |
| Mixing Ratio | Clever Lab. | 80:20 (A:B) |
| Consumption | Clever Lab. | 0.15–0.20 kg/m² |
| Appearance / Colour | Clever Lab. | Matt after full cure |
| Density | Clever Lab. | Component A: 1.05 kg/L Component B: 1.13 kg/L Resin mix: 1.07 kg/L (thin with 5% water.) |
| Product Temperature | Clever Lab. | +10 °C to +30 °C |
| Ambient Temperature | Clever Lab. | +10 °C to +30 °C |
| Working Time | Clever Lab. | +10 °C ~50 min +20 °C ~30 min +30 °C ~20 min |
| Curing Time | Clever Lab. | +10 °C: 24 h – 4 days +20 °C: 16 h – 3 days +30 °C: 12 h – 2 days |
| Time to Traffic | Clever Lab. | +10 °C: 30 h – 48 h +20 °C: 16 h – 24 h +30 °C: 12 h – 18 h |
| Full Cure | Clever Lab. | +10 °C: ~6 days +20 °C: ~4 days +30 °C: ~3 days |
Application
• SURFACE PREPARATION
The pull-off strength must be at least 1.5 N/mm²; in case of doubt, carry out a trial. Before application, the substrate must be clean, dry and free from foreign matter such as oil, grease, coatings and curing compounds. All dust and loose particles must be removed with a brush or vacuum cleaner.
• MIXING
Component A : Component B = 4:1 (by weight) Before starting to mix, homogenise component A mechanically until uniform. Then add all of component B and mix continuously for approx. 3 minutes. For a smoother surface, 5–7% water may be added to the mix. To ensure that the mix is completely homogeneous, transfer it to another container and mix again. Avoid over-mixing to prevent air bubbles.
• APPLICATION
During application, take care to keep joins “wet” to achieve a seamless finish. Apply ClvFloor TC 104 evenly to the surface with a short-pile roller. Before application, check that the relative humidity and dew point conditions are suitable.
The freshly applied coating must be protected from damp, condensation and water for at least 7 days (+20 °C). Before application, make sure the surface is even and clean; thin top coats do not conceal surface irregularities. On epoxy-based surfaces, sanding is recommended for good adhesion; a green pad can be used for this purpose. If heating is required, only electric warm-air blower systems should be used. Gas, oil, paraffin or other fossil-fuel heaters produce CO2 and H2O vapour, which adversely affects the surface appearance. The freshly applied product must be protected from damp, condensation and water for at least 7 days (+20 °C).